Contact Us

+91 20 27120360

Follow Us

PROJECT EXECUTION

Home - PROJECT EXECUTION

PROCESS DESIGN & ENGINEERING

STAGE - 1

The Activities broadly include:

1. Order Approval by client.

2. Final P&I Drawing sent and approval given by client.

3. Process Design and Preparation of Specification Sheets.

4. Final GA and Foundation  Drawing sent and approval
given by client.

5. Mechanical Design and preparation of Detailed
Engineering Drawings.

6. Checking of Drawings and released for fabrication.

 

DESIGN OFFICE

MANUFACTURING & INSPECTION

STAGE - 2

The Activities broadly include:

1.  Estimation and Procurement of Raw Material.

2.  Quality Checks on Raw Material like Material Composition Checks.

3. Fabrication along with Stage wise Inspection.

4.  Final Inspection as per MOJJ QA Plan.

5.     Packing.

 

MANUFACTURING UNIT

SHIPMENT & TRANSPORT TO PORT

STAGE - 3

The Activities broadly include:

1. Export worthy Packing followed by loading and sealing of container.

2. Transportation of container to Mumbai.

3. Custom clearance and loading on vessel.

 

Containerised Cargo

SITE ACTIVITY TO BE UNDERTAKEN BY CLIENT

STAGE - 4

The Activities broadly include:

1. Unloading of container / equipment (in case of oversize cargo)at the destination port.

2. Customs clearance.

3. Internal Haulage to site.

3. Unloading material at site.

 

Internal movement of Cargo to site

PARALLEL ACTIVITY

TO BE COMPLETED BY CLIENT UNTILL STAGE – 4 IS COMPLETED.

— Building Foundation work.
— Dryer Building ,Cut-out and Foundation Checks.
— Unloading the Material at Site.
— Shifting Material and Equipment to actual Location.
— Appointment of Erection Contractor
— Erection of Structural members.
— Procurement of Insulation and Cladding material.
— Procurement of Electrical and Instrument cables and cable trays.
— Procurement of Air Compressor

 

 

Civil Work

SITE ACTIVITY

TO BE UNDERTAKEN BY CLIENT’S CONTRACTOR - STAGE 5

1. Site fabrication of Spray Chamber.
2. Installation of Equipments.
3. Installation of inter-connecting ducting.
4. Mechanical Erection of the Main Equipment and the peripheral Equipment.
5. Installation of Insulation & Cladding on equipments.
6. Installation of cable trays followed by routing of electrical and instrument cables as per cable routing drawings by MOJJ.
7. Electrical Installation.
8. Installation Checks.
9. Commissioning

Installation

 

SITE ASSEMBLY OF SPRAY CHAMBER


 

 

SITE ASSEMBLY OF SPRAY CHAMBER

 

 

 

INSTALLED PLANTS